| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 20 Oct 2025 | 22 Oct 2025 | 100% | Completed |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 22 Oct 2025 | 23 Oct 2025 | 100% | Completed |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 23 Oct 2025 | 23 Oct 2025 | 80% | Fully Allocated |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 24 Oct 2025 | 28 Oct 2025 | 80% | Fully Allocated |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 27 Oct 2025 | 28 Oct 2025 | 80% | Fully Allocated |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 29 Oct 2025 | 31 Oct 2025 | 80% | Fully Allocated |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 29 Oct 2025 | 31 Oct 2025 | 80% | Fully Allocated |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 30 Oct 2025 | 04 Nov 2025 | 80% | Fully Allocated |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 31 Oct 2025 | 04 Nov 2025 | 80% | Fully Allocated |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 12 Jan 2026 | 13 Jan 2026 | 100% | Completed |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 14 Jan 2026 | 20 Jan 2026 | 100% | Completed |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 04 Feb 2026 | 04 Feb 2026 | 80% | Fully Allocated |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 04 Feb 2026 | 10 Feb 2026 | 90% | Fully Allocated |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 09 Feb 2026 | 10 Feb 2026 | 80% | Fully Allocated |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 10 Feb 2026 | 13 Feb 2026 | 80% | Fully Allocated |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 11 Feb 2026 | 16 Feb 2026 | 80% | Fully Allocated |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 16 Feb 2026 | 19 Feb 2026 | 0% | Fully Allocated |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 16 Feb 2026 | 19 Feb 2026 | 0% | Fully Allocated |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 12 Jan 2026 | 13 Jan 2026 | 100% | Completed |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 14 Jan 2026 | 20 Jan 2026 | 100% | Completed |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 04 Feb 2026 | 05 Feb 2026 | 100% | Completed |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 06 Feb 2026 | 11 Feb 2026 | 100% | Completed |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 09 Feb 2026 | 10 Feb 2026 | 100% | Completed |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 10 Feb 2026 | 16 Feb 2026 | 100% | Completed |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 10 Feb 2026 | 16 Feb 2026 | 100% | Completed |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 12 Feb 2026 | 17 Feb 2026 | 100% | Completed |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 18 Feb 2026 | 20 Feb 2026 | 50% | Fully Allocated |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 10 | Apex Roofing | To allow Curtain walling installation- Internal Upstands (inc underlay /insulation & Cap sheet) | 26 Feb 2026 | 03 Mar 2026 | 75% | Material Not Required |
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 09 Mar 2026 | 09 Mar 2026 | 100% | Completed |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 09 Mar 2026 | 09 Mar 2026 | 30% | Fully Allocated |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 10 Mar 2026 | 13 Mar 2026 | 100% | Completed |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 10 Mar 2026 | 13 Mar 2026 | 30% | Forecast Shortfall Order by: |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 16 Mar 2026 | 16 Mar 2026 | 0% | Fully Allocated |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 17 Mar 2026 | 20 Mar 2026 | 0% | Fully Allocated |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 17 Mar 2026 | 20 Mar 2026 | 0% | Fully Allocated |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 22 Mar 2026 | 25 Mar 2026 | 0% | Fully Allocated |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 22 Mar 2026 | 27 Mar 2026 | 0% | Fully Allocated |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 10 | Apex Roofing | To allow Curtain walling installation- Internal Upstands (inc underlay /insulation & Cap sheet) | 26 Feb 2026 | 03 Mar 2026 | 35% | Material Not Required |
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 27 Feb 2026 | 27 Feb 2026 | 100% | Completed |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 02 Mar 2026 | 09 Mar 2026 | 70% | Fully Allocated |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 06 Mar 2026 | 06 Mar 2026 | 0% | Fully Allocated |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 09 Mar 2026 | 10 Mar 2026 | 0% | Forecast Shortfall Order by: |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 10 Mar 2026 | 10 Mar 2026 | 0% | Fully Allocated |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 11 Mar 2026 | 12 Mar 2026 | 0% | Fully Allocated |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 11 Mar 2026 | 12 Mar 2026 | 0% | Fully Allocated |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 12 Mar 2026 | 17 Mar 2026 | 0% | Fully Allocated |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 16 Mar 2026 | 17 Mar 2026 | 0% | Fully Allocated |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 10 | Apex Roofing | To allow Curtain walling installation- Internal Upstands (inc underlay /insulation & Cap sheet) | 02 Mar 2026 | 05 Mar 2026 | 60% | Material Not Required |
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 04 Mar 2026 | 04 Mar 2026 | 40% | Fully Allocated |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 05 Mar 2026 | 12 Mar 2026 | 30% | Fully Allocated |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 06 Mar 2026 | 06 Mar 2026 | 30% | Fully Allocated |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 09 Mar 2026 | 10 Mar 2026 | 30% | Forecast Shortfall Order by: |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 11 Mar 2026 | 11 Mar 2026 | 30% | Fully Allocated |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 12 Mar 2026 | 13 Mar 2026 | 30% | Fully Allocated |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 12 Mar 2026 | 13 Mar 2026 | 30% | Fully Allocated |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 13 Mar 2026 | 18 Mar 2026 | 20% | Fully Allocated |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 17 Mar 2026 | 18 Mar 2026 | 0% | Fully Allocated |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 12 | Apex Roofing | FATRA FHM901 BITUMEN PRIMER | 03 Mar 2026 | 03 Mar 2026 | 100% | Completed |
| Task 13 | Apex Roofing | Primer & Capsheet (field area & upstands) | 04 Mar 2026 | 06 Mar 2026 | 20% | Fully Allocated |
| Task 14 | Apex Roofing | Insulation & seperation layer | 06 Mar 2026 | 07 Mar 2026 | 0% | Forecast Shortfall Order by: |
| Task 15 | Apex Roofing | Finishes | 08 Mar 2026 | 11 Mar 2026 | 0% | Material Not Required |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 12 | Apex Roofing | FATRA FHM901 BITUMEN PRIMER | 03 Mar 2026 | 03 Mar 2026 | 100% | Completed |
| Task 13 | Apex Roofing | Primer & Capsheet (field area & upstands) | 04 Mar 2026 | 06 Mar 2026 | 40% | Fully Allocated |
| Task 14 | Apex Roofing | Insulation & seperation layer | 06 Mar 2026 | 07 Mar 2026 | 0% | Fully Allocated |
| Task 15 | Apex Roofing | Finishes | 08 Mar 2026 | 11 Mar 2026 | 0% | Material Not Required |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 11 | Legacie Contracts | Scaffold dismantle by Legacie Contrats | 16 Mar 2026 | 20 Mar 2026 | 0% | Material Not Required |
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 23 Mar 2026 | 23 Mar 2026 | 100% | Completed |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 24 Mar 2026 | 25 Mar 2026 | 100% | Completed |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 25 Mar 2026 | 25 Mar 2026 | 0% | Fully Allocated |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 26 Mar 2026 | 27 Mar 2026 | 0% | Fully Allocated |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 30 Mar 2026 | 30 Mar 2026 | 0% | Fully Allocated |
| Task 10 | Apex Roofing | To allow Curtain walling installation- Internal Upstands (inc underlay /insulation & Cap sheet) | 30 Mar 2026 | 01 Apr 2026 | 100% | Completed |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 01 Apr 2026 | 03 Apr 2026 | 0% | Fully Allocated |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 01 Apr 2026 | 03 Apr 2026 | 0% | Fully Allocated |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 06 Apr 2026 | 08 Apr 2026 | 0% | Fully Allocated |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 06 Apr 2026 | 08 Apr 2026 | 0% | Fully Allocated |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 10 | Apex Roofing | To allow Curtain walling installation- Internal Upstands (inc underlay /insulation & Cap sheet) | 19 Dec 2025 | 08 Jan 2026 | 100% | Completed |
| Task 11 | Legacie Contracts | Scaffold dismantle by Legacie Contrats | 16 Mar 2026 | 20 Mar 2026 | 0% | Material Not Required |
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 23 Mar 2026 | 23 Mar 2026 | 30% | Fully Allocated |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 24 Mar 2026 | 25 Mar 2026 | 80% | Fully Allocated |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 25 Mar 2026 | 25 Mar 2026 | 0% | Fully Allocated |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 26 Mar 2026 | 27 Mar 2026 | 0% | Fully Allocated |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 30 Mar 2026 | 30 Mar 2026 | 0% | Fully Allocated |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 01 Apr 2026 | 03 Apr 2026 | 0% | Fully Allocated |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 01 Apr 2026 | 03 Apr 2026 | 0% | Fully Allocated |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 06 Apr 2026 | 08 Apr 2026 | 0% | Fully Allocated |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 06 Apr 2026 | 08 Apr 2026 | 0% | Fully Allocated |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 11 | Legacie Contracts | Scaffold dismantle by Legacie Contrats | 16 Mar 2026 | 20 Mar 2026 | 0% | Material Not Required |
| Task 10 | Apex Roofing | To allow Curtain walling installation- Internal Upstands (inc underlay /insulation & Cap sheet) | 16 Mar 2026 | 01 Apr 2026 | 100% | Completed |
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 20 Mar 2026 | 20 Mar 2026 | 100% | Completed |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 23 Mar 2026 | 24 Mar 2026 | 80% | Fully Allocated |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 24 Mar 2026 | 24 Mar 2026 | 0% | Fully Allocated |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 25 Mar 2026 | 26 Mar 2026 | 0% | Fully Allocated |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 26 Mar 2026 | 26 Mar 2026 | 0% | Fully Allocated |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 27 Mar 2026 | 31 Mar 2026 | 0% | Fully Allocated |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 27 Mar 2026 | 31 Mar 2026 | 0% | Fully Allocated |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 30 Mar 2026 | 01 Apr 2026 | 0% | Fully Allocated |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 30 Mar 2026 | 01 Apr 2026 | 0% | Fully Allocated |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 11 | Legacie Contracts | Scaffold dismantle by Legacie Contrats | 16 Mar 2026 | 20 Mar 2026 | 0% | Material Not Required |
| Task 10 | Apex Roofing | To allow Curtain walling installation- Internal Upstands (inc underlay /insulation & Cap sheet) | 16 Mar 2026 | 01 Apr 2026 | 10% | Material Not Required |
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 20 Mar 2026 | 20 Mar 2026 | 100% | Completed |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 23 Mar 2026 | 24 Mar 2026 | 95% | Fully Allocated |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 24 Mar 2026 | 24 Mar 2026 | 0% | Fully Allocated |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 25 Mar 2026 | 26 Mar 2026 | 0% | Fully Allocated |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 26 Mar 2026 | 26 Mar 2026 | 0% | Fully Allocated |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 27 Mar 2026 | 31 Mar 2026 | 0% | Fully Allocated |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 27 Mar 2026 | 31 Mar 2026 | 0% | Fully Allocated |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 30 Mar 2026 | 01 Apr 2026 | 0% | Fully Allocated |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 30 Mar 2026 | 01 Apr 2026 | 0% | Fully Allocated |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 19 Mar 2026 | 20 Mar 2026 | 0% | Fully Allocated |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 21 Mar 2026 | 26 Mar 2026 | 0% | Fully Allocated |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 25 Mar 2026 | 26 Mar 2026 | 0% | Fully Allocated |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 27 Mar 2026 | 01 Apr 2026 | 0% | Forecast Shortfall Order by: |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 01 Apr 2026 | 02 Apr 2026 | 0% | Fully Allocated |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 03 Apr 2026 | 09 Apr 2026 | 0% | Fully Allocated |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 03 Apr 2026 | 09 Apr 2026 | 0% | Fully Allocated |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 09 Apr 2026 | 14 Apr 2026 | 0% | Forecast Shortfall Order by: |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 10 Apr 2026 | 14 Apr 2026 | 0% | Material Required Order by: |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 06 Apr 2026 | 06 Apr 2026 | 30% | Fully Allocated |
| Task 10 | Apex Roofing | To allow Curtain walling installation- Internal Upstands (inc underlay /insulation & Cap sheet) | 06 Apr 2026 | 24 Apr 2026 | 55% | Material Not Required |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 07 Apr 2026 | 14 Apr 2026 | 30% | Fully Allocated |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 14 Apr 2026 | 14 Apr 2026 | 20% | Forecast Shortfall Order by: |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 15 Apr 2026 | 16 Apr 2026 | 20% | Forecast Shortfall Order by: |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 16 Apr 2026 | 16 Apr 2026 | 20% | Material Required Order by: |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 17 Apr 2026 | 20 Apr 2026 | 20% | Forecast Shortfall Order by: |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 17 Apr 2026 | 20 Apr 2026 | 0% | Forecast Shortfall Order by: |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 21 Apr 2026 | 24 Apr 2026 | 0% | Forecast Shortfall Order by: |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 23 Apr 2026 | 24 Apr 2026 | 0% | Material Required Order by: |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 28 Apr 2026 | 29 Apr 2026 | 0% | Fully Allocated |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 30 Apr 2026 | 06 May 2026 | 0% | Fully Allocated |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 05 May 2026 | 06 May 2026 | 0% | Material Required Order by: |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 07 May 2026 | 12 May 2026 | 0% | Forecast Shortfall Order by: |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 11 May 2026 | 12 May 2026 | 0% | Material Required Order by: |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 13 May 2026 | 19 May 2026 | 0% | Material Required Order by: |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 13 May 2026 | 19 May 2026 | 0% | Material Required Order by: |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 18 May 2026 | 21 May 2026 | 0% | Forecast Shortfall Order by: |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 19 May 2026 | 21 May 2026 | 0% | Material Required Order by: |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 20 Oct 2025 | 20 Oct 2025 | 100% | Completed |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 21 Oct 2025 | 24 Oct 2025 | 100% | Completed |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 19 Jan 2026 | 19 Jan 2026 | 100% | Completed |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 20 Jan 2026 | 22 Jan 2026 | 100% | Completed |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 23 Jan 2026 | 23 Jan 2026 | 100% | Completed |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 24 Jan 2026 | 27 Jan 2026 | 100% | Completed |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 26 Jan 2026 | 28 Jan 2026 | 100% | Completed |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 28 Jan 2026 | 30 Jan 2026 | 100% | Completed |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 28 Jan 2026 | 03 Feb 2026 | 100% | Completed |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 15 Dec 2025 | 15 Dec 2025 | 100% | Completed |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 16 Dec 2025 | 19 Dec 2025 | 100% | Completed |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 27 Jan 2026 | 27 Jan 2026 | 100% | Completed |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 28 Jan 2026 | 30 Jan 2026 | 100% | Completed |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 30 Jan 2026 | 30 Jan 2026 | 100% | Completed |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 02 Feb 2026 | 04 Feb 2026 | 100% | Completed |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 02 Feb 2026 | 04 Feb 2026 | 100% | Completed |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 03 Feb 2026 | 05 Feb 2026 | 100% | Completed |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 03 Feb 2026 | 05 Feb 2026 | 100% | Completed |
| Task | Assigned | Description | Start | End | Progress | Material Status |
|---|---|---|---|---|---|---|
| Task 1 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 15 Dec 2025 | 16 Dec 2025 | 100% | Completed |
| Task 2 | Apex Roofing | IKO ULTRA T-O VCL LAYER (field area & Upstands) | 17 Dec 2025 | 23 Dec 2025 | 100% | Completed |
| Task 3 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 27 Jan 2026 | 27 Jan 2026 | 100% | Completed |
| Task 4 | Apex Roofing | Upstand & Field Area Insulation | 28 Jan 2026 | 29 Jan 2026 | 100% | Completed |
| Task 5 | Apex Roofing | IKOpro BONDING AGENT (field area & Upstands) | 30 Jan 2026 | 30 Jan 2026 | 100% | Completed |
| Task 6 | Apex Roofing | IKO FIELD AREA UNDERLAY | 02 Feb 2026 | 03 Feb 2026 | 100% | Completed |
| Task 7 | Apex Roofing | IKO DETAILING UNDERLAY (upstands) | 02 Feb 2026 | 03 Feb 2026 | 100% | Completed |
| Task 8 | Apex Roofing | IKO FIELD AREA CAP SHEET | 03 Feb 2026 | 05 Feb 2026 | 100% | Completed |
| Task 9 | Apex Roofing | IKO UPSTAND CAP SHEET | 03 Feb 2026 | 05 Feb 2026 | 100% | Completed |